AY pumping station

This central pumping station for the Tel-Aviv Metropolis wastewater was built 30 meters under the ground, as was required by the deep gravitational line that delivered the wastewater to the station.

The station, which was constructed inside underground water, actually consists of two stations, the second serving as an emergency pump in case the first is flooded.

Each station will have 2 pumps (4 pumps altogether), with a pumping ability of some 4,000 cubic meters / hour.
Project scope will be approximately NIS 150 million ($43 million). It is expected to end in 2013.